Release Assembly to Production


The Release Assembly to Production function is used in with the Engineering Change Order Process.
Normally a Bill of Materials may be changed by any user that has the rights to the Assembly Screen.
This is usefull when the research and devolopment team are doing the initial design.
In this mode the revision tracking is not mandatory and is up to the user if they want to update the revision.
Once an Assembly is Released to Production it is no longer able to be directly edited in the assembly screen.
The User must create an Engineering Change Order to list all the changes and have it approved before applying it to the BOM.
In order to apply the changes the revision must be changed.
This allows a full history tracking on all the changes made to a Bill of Materials.